We were appointed to carry out full roofing works on a remote Network Rail PSP location, accessed via a disused 2-mile tunnel. The job demanded a high level of planning, adaptability, and on-site coordination due to its challenging access and strict safety requirements.

Despite obstacles, Safeseal completed the full roofing system installation without delay, delivering a robust and maintenance-friendly finish.
The project aimed to deliver a high-quality roofing installation within a challenging and remote location, meeting strict Network Rail standards while maintaining safety and efficiency. Key goals included overcoming complex site logistics, ensuring smooth delivery of materials through limited access routes, and achieving a durable, maintenance-friendly finish. Our objective was not only to complete the works on time and to specification but to demonstrate the team’s capability, reliability, and professionalism to secure ongoing partnerships with Network Rail.
The project’s remote location presented a major challenge, as the PSP line could only be accessed through a two-mile abandoned tunnel, creating significant logistical barriers for delivering materials, equipment, and workforce. With no standard access routes available, moving trusses, fixings, and roofing materials demanded meticulous planning and strong teamwork to keep progress on track. Despite these complexities, the work had to be completed quickly, safely, and in full compliance with Network Rail standards.
Despite the obstacles, we completed the full roofing system installation without delay, delivering a robust and maintenance-friendly finish. Our team used premade trusses to create a strong structural framework, UPVC fascias, soffits, and rainwater goods to achieve a clean, low-maintenance edge, and Roofshield breathable felt with treated battens for dependable weatherproofing. The tiled roof was finished with a secure dry verge and dry ridge system, ensuring long-term durability and a neat, professional appearance. Although the remote access required careful coordination of every delivery and material movement, the site team kept operations running smoothly from start to finish.
We completed the project one week ahead of schedule, delivering a high-spec finish in a logistically challenging location. Our team’s performance, efficiency, and reliability not only ensured a smooth delivery but also secured further work with Network Rail as a result of our proven capability on this project.
"Safeseal handled a highly complex, logistically challenging project with exceptional organisation and workmanship - their professionalism made the whole process seamless."
This project showcased our ability to handle complex, logistically challenging works without compromising on quality or timeframes. By staying adaptable, working as a team, and maintaining high standards throughout, we delivered ahead of schedule - even in one of the most difficult access environments we’ve faced. Our performance on this scheme led directly to further opportunities with Network Rail, reinforcing our reputation as a dependable roofing partner for high-pressure, high-spec projects.